Piping Drawing Review Process

0

Piping Drawing Review Process

The review of piping drawings should be conducted using printed copies or check plots, with colored pencils or pens for clarity. The following guidelines apply:

  • Yellow: Highlights corrected areas and dimensions.
  • Green: Marks areas and dimensions to be removed.
  • Red: Indicates areas to be corrected or added on the drawing.
  • After corrections are made, the new print is reviewed again ("back checked") to ensure the changes have been properly incorporated.

Key Aspects to Review in Piping Drawings:

  1. Drawing Title: Ensure the title is correct and complete.
  2. Orientation: Verify the north arrow is aligned with the plot plan.
  3. Graphic Scale: Confirm inclusion, especially if the drawing will be scaled down.
  4. Equipment Coordinates: Check against the equipment layout for accuracy.
  5. Equipment Numbers: Confirm they are displayed correctly on the piping drawing.
  6. Line Identification: Ensure all lines are correctly labeled in all views.
  7. Line Specification Changes: Check if changes in line specifications are properly indicated.
  8. Reference Drawings: Confirm all reference drawing numbers and files are correct.
  9. Dimensions: Verify the correctness of all dimensions shown.
  10. Symbol Accuracy: Ensure that symbols match standard representation guidelines.
  11. Instrument Identification: Check all instruments are correctly labeled.
  12. Straight Length Requirements: Verify required upstream/downstream straight lengths.
  13. Insulation Needs: Confirm insulation specifications as per P&IDs.
  14. Piping Arrangement: Ensure it meets the P&ID requirements, such as gravity flow and seals.
  15. Interference Check: Look for potential interferences in the piping design.
  16. Scale Accuracy: Confirm scale accuracy, especially in general arrangement drawings.
  17. Stress Analysis Compliance: Ensure all stress analysis requirements are satisfied.
  18. Clearances: Check for sufficient clearance from civil structures, electrical systems, and instrument consoles.
  19. Openings: Confirm the adequacy of floor and wall openings.
  20. Accessibility: Ensure operational and maintenance spaces are accessible, with space for drop-out areas and handling.
  21. Foundation and Vendor Requirements: Confirm the foundation drawings and vendor specifications are incorporated.
  22. Sections and Details: Ensure section identifiers and details match.
  23. Match lines: Verify accuracy of match line locations.
  24. Signatures and Dates: Ensure drawings are signed and dated.
  25. BOM Accuracy: Confirm the Bill of Materials (BOM) in isometric drawings is correct.
  26. Revision Number: Check the number of issues and revisions is up to date.

This process ensures a comprehensive and accurate review of piping drawings, adhering to standards and project requirements.